Construction to replace sewer lines and manhole structures
Efforts to improve the watershed system throughout DeKalb County continue Monday, April 7, with the launch of the Gravity Sewer Rehabilitation and Replacement Project.
Crews will replace approximately 1,230 feet of gravity sewer main on Keheley Drive between Windell Drive and Melody Lane. This sewer improvement project is expected to last approximately four months (April 2025 to August 2025), barring any weather delays.
Normal construction hours will be from 7 a.m. to 7 p.m., Monday through Friday, excluding major holidays. An increase in construction-related noise and traffic during work hours should be expected.
To learn more about the Gravity Sewer Rehabilitation and Replacement Project, join the virtual community meeting on Thursday, April 3, 6:30 p.m., via Zoom at https://dekalbcountyga.zoom.us/j/81135072486
Information also can be obtained by calling the DWM Project Information Line at 1-800-986-1108 or emailing projectinfo@dekalbcountyga.gov with questions.