Event Calendar

Construction Update

 

PDK Runway 3R/21L Keel Replacement Project

 

The Runway 3R/21L Keel Replacement Project is underway as of September 1, 2025. The duration of the entire construction project is scheduled to be 105 days. We are currently in Phase 2 and both RWY 3R/21L and RYW 16/34 are closed. Please continue to plan accordingly with this secondary closure and note that Runway 3L/21R is the only runway open during this time. Please feel free to contact the Airport Administration Office if you have any questions or concerns.

 

 

PDK Runway 3R/21L Project

3R/21L Keel Project Memo 5-25-25

3R/21L Keel Project Memo 7-18-25

3R/21L Keel Project Memo 7-28-25

3R/21L Keel Project Memo 8-1-25

3R/21L Keel Project Memo 8-20-25

3R/21L Keel Project Memo 10-2-25

Runway 3R/21L Keel Project Phasing Map

 

 

PDK Airfield LED Project

The LED Project is in its final stages; all of the airfield lighting as been completed including the Helipad. The generator for the airfield lighting has been installed and tested. Over the course of the next several weeks we will be running through final checks and getting prepared to close out the projects. If you have any question please contact the Airport Administration Office 770-936-5440

 

 

Airfield Picture

 

PDK Airfield LED Project - March 3rd 

Phases 1 -5

Phases 6 -9

Initial Project Memo - February 10, 2025

Project Update Memo - April 7, 2025

Project Update Memo - April 24, 2025

 

 

Notice to the Public Regarding Construction: Disadvantaged Business Enterprise (DBE) Goal for PDK