Scott Boulevard Water Main Replacement Project Phase III

Map

The Scott Boulevard Water Main Replacement Project Phase III has been designed to improve the watershed system in Decatur, Georgia. Impacted Stakeholders can learn about the project below. 

Notification LetterCommunity MeetingPress Release & Social Media 

Project Start Date: 

August 2023

Timeframe: 18 months from start to finish

Project Start Letter

Notification Letter: Oct. 27, 2023

Notification Letter: Nov. 14, 2023

Door Hanger: Mar. 21, 2024

Notification Letter: Aug. 1, 2024

Project Update: Aug. 15

Project Update: Aug. 19

Project Update: Aug. 26

Project Update: Sept. 9

Project Update: Sept. 17

Project Update: Sept. 23

Project Update: Sept. 30

Project Update: Oct. 7

Project Update: Oct. 21

Project Update: Oct. 29

Project Update: Nov. 12

Project Update: Dec. 4

Door Hanger: Jan. 23

Door Hanger: Jan. 23

Door Hanger: Jan. 23

Project Update: Jan. 28

Door Hanger: Feb. 3

Project Update: Feb. 3

Project Update: Feb. 12

Door Hanger: Feb. 13

 

DeKalb County Engineering and Construction Management hosted a virtual meeting for the Scott Boulevard Phase III Water Main Replacement Project.

Residents and business owners impacted by the project had the opportunity to learn about how the project will impact service delivery, traffic, and community schedules. See below: 

Youtube Meeting Recording

 Project Update Public Community Meeting Presentation

 

 As part of DeKalb County’s $2.4 billion capital improvement program, the Department of Watershed Management (DWM) will be improving the capacity and service of the Watershed systems in DeKalb County. See here: DeKalb County Press Release for the Scott Boulevard Phase III Water Main Replacement Project

Nextdoor Notification

 

 

 

     ScScott III